Big works on a building go wrong in the same ways: nobody agreed the scope, the price changed, owners were not told and the work was not supervised. A simple process avoids most of that.
1. Assess the need
Start with an inspection. Facades and internal stairwells commonly need attention between the seventh and tenth year, and mechanical parts such as lifts have their own cycle. A property manager who inspects regularly will already have a list.
2. Define the scope
Write down what will be done and what will not. If the work is large, a professional assessment is worth having.
3. Obtain several quotations
Ask more than one contractor to price the same scope. Compare like with like, and look at what is excluded as well as at the total.
4. Check the budget
Costs should sit within the budget approved by the owners. If they do not, that must be raised before the work is awarded.
5. Get owners’ approval
Where funds from a sinking fund or extra contributions are involved, owners decide, typically at an AGM or EGM. Give them the quotations and a plain explanation.
6. Supervise the work
Someone needs to be the link between residents and tradesmen. The property manager monitors the services provided and reports back to residents.
7. Pay and report
Payments to subcontractors are made against the work done. When the job ends, residents should receive a report of the works carried out and the costs incurred.
8. Follow up
Check the work again after completion, keep the paperwork and note any warranties.
Do it yourself or appoint someone?
A committee of owners can run this, but it takes time and expertise. Appointing a project manager, often the administrator, keeps one person accountable.
Read about our project management service, or how we administer condominia.